Reconstruction of the waste water treatment plant and completion of construction of sewerage in Ústí nad Orlicí
On Tuesday, July 14, 2015 a ceremonial completion of the project “Ústí nad Orlicí – sewerage and WWTP“ was held. A higher quality and more efficient solution of the problem of waste treatment and environmental protection in Ústí nad Orlicí District are achieved thanks to implementation of this project.
For connection of additional 2,900 inhabitants to the sewerage network ended by the waste water treatment plant 26.527 km of new sewerage networks was constructed with 25 pumping stations, approx. 5.85 km of the existing sewerage networks was reconstructed and intensification of the waste water treatment plant in Ústí nad Orlicí was carried out in order to reduce the amount of the pollution discharged at the selected indicators. The works were performed in the period from July 2012 to May 2014 and then a year long trial operation followed. All these binding parameters have been met by the implementation.